Maximize your protection, eliminate business risks.
Optimize and modernize with cloud transformation.
Empower your people to work securely from anywhere.
Let us handle IT so you can focus on growing your business.
Get multichannel 24/7/365 expert end-user support.
Protect, detect, and respond—Dataprise keeps your business secure.
Maximize uptime with with industry-leading DRaaS.
Swiftly mitigate cyber threats and restore security.
Improve efficiency, productivity and outcomes with cloud.
Ensure all mobile devices, everywhere, are secure.
Gain a competitive edge with strategic IT solutions.
This battle-tested checklist enables your team to swiftly initiate a ransomware response.
IT for businesses of all sizes, in any industry.
Empower institution growth with custom IT solutions.
Ensure your firm is always in compliance.
Improve patient care and staff morale.
Deal with pressing legal matters, not IT.
Keep up with the evolving digital landscape.
Focus on your mission by outsourcing IT.
Accelerate PE client deals and secure data.
Empower Your Municipality with Secure, Reliable IT Services
Execute initiatives and develop IT strategies.
Get the latest industry insights and trends.
Join us at events in person and online.
Hear from clients and learn more about strategic IT.
See how Dataprise can make IT your greatest asset.
Get informative technical resources from IT experts.
Stay on stop of emerging cybersecurity threats.
Discover the key areas of DR your organization needs to address to ensure downtime is minimized.
Gain a strategic asset by bringing harmony to IT.
Ensure 24/7 support and security with dedicated teams.
Drive business forward by partnering with Dataprise.
Meet our one-of-a-kind leadership team.
Discover the recognition Dataprise has earned.
Help us help businesses with strategic IT.
Grow through acquisition and partnership with Dataprise.
Embracing different perspectives and backgrounds.
Find a Dataprise location near you.
Dataprise is committed to empowering more women to consider a career in technology.
Explore our trusted partnerships with leading tech innovators.
Posts
By: Dataprise
Table of content
Microsoft Project – Fixed Duration, Fixed Units and Fixed Work
One of the more difficult scheduling aspects in using Microsoft Project to schedule effort driven work is the concept of Fixed Duration, Fixed Units and Fixed Work. I have heard numerous colleagues including myself at times say “what’s wrong with Microsoft Project, its changing the schedule in crazy ways when resources are added or subtracted”. In fact, Microsoft Project is functioning correctly once one understands the way fundamental way it works.
Microsoft Project, when scheduling tasks based on effort driven schedules allows the project manager to work with three different variables. The project manager can only control two of these variables while Microsoft Project always automatically calculates the third. These variables are:
1. Fixed Units
2. Fixed Duration
3. Fixed Work
It is critical for a project manager to have a comprehensive understanding of the implications of each of these variables.
Fixed Units suggests that are the amount of capacity that a resource can devote to a task. An example of this is that you suggest to Microsoft Project that a resource can only work 50% of the time on a specific task. Microsoft Project will then automatically calculate the duration of the task with the resource only working 50% of the time.
Fixed Duration suggested that the task the task must be completed within a given duration. As you assign a single or multiple resources to the task, Microsoft Project will automatically calculate the appropriate resource allocation percentage to ensure the task is completed within the given duration.
Fixed Work suggests that a task has a specific numbers of hours work associated with it. In this scenario, we know that the task is going to take ten hours to complete. We have the ability to schedule the tasks overall duration for five days with fixed work of ten hours. Assuming a single resource is responsible for completing the task, Microsoft Project will schedule the resource to work two hours a day for the five day duration.
There are several advanced scheduling scenarios that can influence what is discussed above including front, middle and back loading of resources which aren’t addressed in this blog.
Dan Thompson, PEI